What happens in the Gantt chart scheduling when I change the end date of a task via the bulk scheduling in the task log?

Here we will look at the changes that occur when you update the end date via the bulk scheduling option in the task log.

Within the Method grid platform, you have always had the option to change the end date of tasks via the bulk scheduling tool, in the task logs.

We still have both the element task log, and the grid task log.

Please Note: Tasks with end dates updated with bulk scheduling, will have these End Dates reflected in the Gantt Chart.

Within the Gantt Chart, the corresponding tasks will show Constraint Date, End Date & Start Date all equal to the imported date, the Constraint Type set to 'Must Finish On', and the Duration set to '0 Days'. See here: 

Here we will look at how updating dates in the task logs will be reflected in the Gantt: